Before asking for a quote, one of the most common questions is how much time the work will take day to day. The answer depends on several factors: the size of the home, its current condition, whether it is occupied or empty, and the time of year you book.
Factors that determine the project timeline
Not all apartments take the same time to paint, even if they have similar square metres. These are the factors that matter most:
- Total area: a small apartment of 50-60 m² can be completed in 2-3 days, while one of 100-120 m² may need between 5 and 7 days.
- Condition of walls: cracks, dampness or degraded plaster require surface preparation before painting, which adds days to the schedule.
- Textured ceiling or walls: removing texture and smoothing the surface can add several extra days, as it requires a different preparation process than painting directly.
- Occupied or vacant home: working with furniture inside means protecting and moving objects room by room, which slows down the work pace.
- Number of workers: a team of two people significantly reduces the days compared to working alone.
Peak season: when demand is highest
Spring and summer usually concentrate much of the renovation and painting work, as they coincide with house moves, holidays and better conditions for ventilation after painting. This means busier schedules among professionals and, at times, longer waits to secure a date. September and October are also months of high demand, coinciding with the return to routine and the desire to have the home ready before the holidays.
Low season: an opportunity to plan with plenty of time
The first months of the year and part of autumn usually have less volume of ongoing work, which means clearer schedules among professionals. Booking during those periods not only makes it easier to find availability further in advance, but also leaves more room to coordinate tasks such as wall smoothing without having to rush the calendar.
How to plan the work without losing days along the way
Once you have decided on the right time, there are specific steps that help ensure the agreed timeline is met and not extended by unexpected issues.
- Ask for the quote to be calculated after the professional has seen the space, either through photos and videos or with a visit; both options work equally well to assess the real condition of the walls.
- Put in writing which rooms are to be painted, with what finish and in what order, to avoid last-minute adjustments that delay the schedule.
- Ask how many workers will be working at the same time, as a team of two people significantly reduces the days compared to working alone.
- Plan in advance the access to each room (furniture, appliances, fragile objects) to avoid wasting work hours on the first day.
On our platform, quotes per m² are always treated as an indicative figure, because two spaces with the same area can be in very different conditions (cracks, dampness, degraded plaster). The final price is only confirmed after assessing the real condition of the walls, and that is why photos and videos are always requested before closing any quote, precisely to avoid surprises in timeline or cost mid-work. In addition, all agreed scope (rooms, finishes, dates) is recorded online, visible to the client, the professional and the platform, which prevents misunderstandings about what was painted and in what timeframe.
Frequently Asked Questions
With the apartment empty and two painters working, it usually takes 3 to 4 days. If the home is occupied or walls need preparation, the timeline can go up to 5 to 8 days.
Summer speeds up drying and makes ventilation easier, but it is also the peak demand season, with less professional availability. Winter makes it easier to find availability, although you should allow for slightly longer drying times.
It depends on the type of paint, but as a general guideline it is best to wait at least 24 hours after the last coat before leaning objects against the wall, although full curing may take several more days.
Yes, removing texture and smoothing the surface can add several extra days to the initial schedule, as it requires a different preparation process than painting directly onto a smooth wall.
It is possible, although the work takes longer because you need to protect and move furniture room by room. If the schedule is tight, emptying the home or painting by zones is usually the fastest option.